STAFFORD COUNTY - TEXT ONLY SITE

  Home > Departments > Purchasing > Vendor's Guide to Doing Business with Stafford
Supplemental Specificiations

SS-1 Quantities shown on the bid sheet shall not be construed to represent the actual amount of work to be completed under this contract, but rather they are to be used only for the purpose of evaluation of bids.

SS-2 Engineer shall be defined as Frank Cox, The Cox Company.

SS-3 Owner shall be defined as Board of Supervisors, County of Stafford, Virginia.

SS-4 Any excess materials shall be disposed of by the Contractor at a location secured by himself. If the Contractor wishes, he may dispose of excess material at the County landfill at no cost.

SS-5 Nothing herein is intended to exclude any responsible vendor, his product or service or in any way restrain or restrict competition. On the contrary, all responsible vendors are encouraged to bid and their bid is solicited. Comments as to how specifications could be improved are welcome.

SS-6 Attention is called to the Code of Virginia, Section 11-20.2, concerning the withdrawal of bids for County contracts under certain circumstances.

SS-7 Stafford County follows procedure number one (1) contained in that section for the withdrawal of bids, "The bidder must give notice in writing of his claim or right to withdraw his bid within two (2) business days after the conclusion of the bid opening procedure."

SS-8 It shall be the Contractor's responsibility to locate and properly protect from damage during construction any and all existing pipe lines, structures and utilities. The Contractor shall keep a properly operating underground pipe locator on the job at all times. The Contractor shall contact "Miss Utility" two (2) full working days, excluding weekends and Holidays, before beginning excavation in a particular area.

SS-9 Changes in the work and changes in the contract price shall be as follows:

1. The Owner may, by written change order to the Contractor, make alterations in the plans involving increases or decreases in the quantity of work as may be necessary or desirable. Such alterations shall not be considered as a waiver of any of the conditions of the contract, nor invalidate any of the provisions thereof.

2. Extra work made necessary by alteration of the plans or found necessary by the Engineer during construction and limited to work other than that required to complete the improvement as detailed on the plans or specifications where applicable, shall be done in accordance with the best practice as approved by the Engineer provided, however, that before any extra work is started, a written change order, from the Engineer and approved by the Owner, shall be delivered to the Contractor.

SS-10 PARTIAL PAYMENTS
A. Partial payments may be made monthly on the basis of ninety-five percent (95%) of the value of the work satisfactorily completed subject to the following:
1. the work is progressing satisfactorily;

2. the orders of the Owner have been fulfilled;

3. the time of completion has not expired; and

4. pending the Board of Supervisors approval for payment.

B. Before making any partial payment, the Owner may require the Contractor to present a verified written statement showing the amounts owed for labor performed and materials furnished along with the names and addresses of the persons to whom such sums are due. In case the Contractor shall have sublet a part of this work, the statement shall also show the sum owed to the subcontractor and be accompanied by a verified statement of the Subcontractor showing names and addresses of persons performing labor or furnishing material under that subcontract along with the respective amounts due such persons.

The Owner may pay the amounts due directly to the creditors of the Contractor or Subcontractor so listed, deducting amounts from that due the Contractor or Subcontractor.

C. Partial payments made by the Owner to the Contractor are monies advanced for the purpose of assisting the Contractor to expedite the work under this Contract. The Contractor shall be responsible for the care and protection of all materials and work upon which payments have been made until the acceptance of such work and materials by the Owner.

D. Any such partial payment shall not constitute a waiver of the right of the Owner to require the fulfillment of all terms of the Contract, and the delivery of all improvements embraced therein, complete and satisfactory in all details.

SS-11 WITHHOLDING PAYMENTS
A. The Owner may withhold from any payment otherwise due the Contractor so much as may be necessary to protect the Owner. The County may also elect to withhold any amounts the Contractor owes to any Subcontractor or material dealers for work performed or materials furnished to them.

B. Any amount due to the Owner for liquidated damages, or other purposes as provided under the terms of this Contract, shall be deducted from the final payment due to the Contractor.

C. The failure or refusal of the Owner to withhold any monies from the Contractor shall in no way impair the obligation of any surety or sureties under any bond or bonds furnished under this Contract.

SS-12 The Contractor is to be advised that the County of Stafford will make every effort to process all payments and to issue the approved check within thirty (30) days after receipt of the approved monthly partial payment request.

SS-13 The Contractor shall make all repairs due to defective workmanship or materials for the term of one (1) year after the final acceptance date and shall correct and repair promptly during the time all defective work and material of whatever description. However, ordinary wear and tear or damage due to negligent or improper operation or maintenance on the part of the Owner shall not be considered any obligation of the Contractor. In the case the Contractor shall neglect or fail to promptly make said repairs, after written notifications, the Owner shall cause such repairs to be made at the expense of the Contractor and/or his surety.

SS-14 Every effort to equitably settle all claims, disputes and other matters in question shall be made between the Owner and the Contractor. The Contractor will carry on the work and maintain he progress schedule during the process unless otherwise mutually agreed in writing. If perchance, the aforementioned claims, disputes and/or other matters in question cannot be mutually agreed upon, then such matters shall be processed through the appropriate judicial court system.

SS-15 Contractor to pay all fees and obtain all permits.


Send this
to a friend

 
Contact Us | Home | Privacy | Site Disclaimer | Commonwealth of Virginia | U.S. Government Portal | Exchange Login | Mdaemon Employee Login
  Questions or comments? Send us an email.


PLEASE NOTE: Any e-mail sent to a member of the Board of Supervisors, or any other public official and/or employee of Stafford County, becomes a public document and is subject to the Virginia Freedom of Information Act. This means that a copy of any such e-mail could be requested by a citizen, or a member of the media, is subject to disclosure, and could be reprinted and/or used in a public forum.

1300 Courthouse Road, P.O. Box 339, Stafford, Virginia 22555-0339
Phone: (540) 658-8603, Fax: (540) 658-7643, Metro: (703) 690-8222



 

Copyright © 2008 All Rights Reserved